Pat,
I've sent the package to the different Madison utilities, so could you just check the "no facilities" box on the DT1077 form for MUFN, sign it, and email or snail mail that back to me?
I'll be in touch again in about a year for the next project, near Femrite Drive.
Thanks much,
Sean

From: Patrick Christian [mailto:patrick.christian at wisc.edu]
Sent: Monday, September 17, 2018 11:59 AM
To: Hadfield, Sean M - DOT (DTSD Consultant) <Sean.Hadfield at dot.wi.gov>; MUFN-1077 at lists.mufn.org
Cc: Klang, Marvin <klang at countyofdane.com>; Dan Parenteau <dan.parenteau at wisc.edu>
Subject: RE: WisDOT projects 1007-12-74, -75: I-39 from CTH AB to USH 12/18 Interchange

Herb - neither MUFN nor the City of Madison have any infrastructure south of the Hwy 12/18 & I-90 interchange.  However, on the North side of the Hwy 12/18 & I-90 interchange both the City and Dane County have infrastructure (namely Femrite Dr).

Sean - given the lack of facilities in the WisDOT work area, do you need signatures from all entities (MUFN, City of Madison, Dane County) saying we don't have facilities in the WisDOT project area?

Thanks,
Pat



Thanks,
Patrick L. Christian
Asst. Director, Network Services
UW-Madison Division of IT (DoIT)
1210 W. Dayton St
Madison, WI 53706
Desk (w/ V-mail): 608.265.9699
Cell: 608.516.3264
Fax: 608.262.4679
patrick.christian at wisc.edu<mailto:patrick.christian at wisc.edu>

Let's go RED ... and ON Wisconsin!!!



From: Mufn-1077 [mailto:mufn-1077-bounces at lists.mufn.org] On Behalf Of Hadfield, Sean M - DOT (DTSD Consultant)
Sent: Monday, August 20, 2018 8:10 AM
To: MUFN-1077 at lists.mufn.org<mailto:MUFN-1077 at lists.mufn.org>
Cc: DOT I39 Project <I39Project at dot.wi.gov<mailto:I39Project at dot.wi.gov>>
Subject: [Mufn-1077] WisDOT projects 1007-12-74, -75: I-39 from CTH AB to USH 12/18 Interchange

Utility manager,
Attached are a cover letter, project overview map, an acknowledgment form (#DT1077), and a list of other utilities in the area, for upcoming WisDOT projects 1007-12-74 and -75 on I-39/90 for the south approach to the Beltline Interchange.
Please return the acknowledgement form within 7 days and any maps you could provide within 60 days, to help us keep our design on track and design to avoid utility conflicts and to comply with State Statute TRANS220.
Respectfully,

Sean M. Hadfield, P.E.
I39/90 Corridor Utility Coordinator
AECOM
608-828-8141
sean.hadfield at dot.wi.gov<mailto:sean.hadfield at dot.wi.gov>

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.mufn.org/pipermail/mufn-1077/attachments/20180917/e52fd4fa/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: DT1077_MUFN_COMLN_10071274.pdf
Type: application/pdf
Size: 63498 bytes
Desc: DT1077_MUFN_COMLN_10071274.pdf
URL: <http://lists.mufn.org/pipermail/mufn-1077/attachments/20180917/e52fd4fa/attachment-0001.pdf>


More information about the Mufn-1077 mailing list